Residents’ Christmas Newsletter from the Harry Fairclough site team

Dear Neighbour,

We have been a part of your community for over 12 months now and the Knapping Mount site has come a long way in that time. As we enter the final stage of the project we wanted to thank you for making us welcome and for your continued patience throughout the build process. We appreciate that living next to a live building site can be inconvenient at times and we are very much looking forward to completing the project in the Spring and handing over a building that will serve the Harrogate district for many years to come.

Christmas site hours

 The site will officially close for Christmas on Friday 23rd December and we will be back in action on the Tuesday 3rd January 2017. 24 hour security will be operational during the festive period and if you have any questions or concerns about the site during this time please feel free to comment on our blog which will be frequently monitored – www.harrogatecivichq.com

 New year, new phase  

 The next major phase of activity on site will include installation of the final section of steelwork to the canopy area by Gate 2. We will then be focussing on ‘closing in’ the building and continuing roofing so that the internal works can progress, we will also be commencing the external works to the scheme. As the building progresses you will start to see its innovative design come to life along with the architect’s vision of an enjoyable and vibrant place for people to work and visit that supports modern working practices and allows the Council’s services to work together on the same site.

 Parking and vehicle movement  

Unfortunately, we have had to close the main site car park due to the sheer amount of materials being delivered to site, as it was no longer safe to keep it open. Wherever possible, our site team is using local public car parks but there are times when tools or materials need to be brought to site and it is necessary to park in neighbouring streets or pull up or queue outside the site entry points. We are aware that parking is tight around the site and are doing all that we can to minimise on-street parking and manage deliveries efficiently to alleviate this wherever we can.

 Our community commitment

 Since the beginning of the project we have supported the local community by providing employment opportunities, building partnerships and giving young people an opportunity to be a part of this exciting build. We are very proud to report that over 90% of our subcontractors are based locally and we continue to provide opportunities to local businesses. Our partnership with Harrogate College is going strong and we currently have electrical students visiting site to gain valuable, hands on experience. Local schools are working hard to complete artwork that will be displayed in the finished building, and have also visited the site to plant trees. Our schools and college programme will continue until the end of the project so please get in touch if you are interested in finding out about how your local school could get involved.

For further information about our work with the local community please visit our site blog www.harrogatecivichq.com where you will find regular updates from our site team.

 Wishing you a very Merry Christmas and a Happy New Year, Peter and the Harry Fairclough site team

 

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s